Introduction
Project introduction:JINPENG contracts EPC turnkey service of this project, including metallurgical experimental study,engineering design,equipment manufacture and installation&commissioning etc.
Project process:By lots of metallurgical tests, final processing flow is one rougher,one scavenger and three times cleaners flotation separation+high intensity magnetic separation for tailing from flotation separation.
Final concentrate grade:5.2%
Recovery rate of concentrate:72%