Introduction
Project introduction:JINPENG contracts EPC turnkey service of this project, including metallurgical experimental study,engineering design,equipment manufacture and installation&commissioning etc.
Project process:Based on metallurgical test report, flotation separation process is adopted, which is one time rougher,two times scavengers,seven times cleaners and the concentrate from the forth time cleaner being reground.
Final concentrate grade:97.50%
Recovery rate of concentrate:92.00%